Concrete work has been postponed again until next week. I will try to keep you informed as best I can on the start time and cure time.

Painting is now scheduled to begin on August 12.  If you have submitted a color change and not received an approval from me, please send me a reminder. I don't want anything to fall through the cracks.

If you are behind on getting any repairs done, let me know so I can try to push your painting further back. At this time I can try to accommodate specific requests for timing, but I can make no guarantees on them.  Let me know if you have a particular need and I will see what I can do.

My laptop computer has achieved a near death experience and is being resuscitated at a top secret facility out of town. As soon as it returns I will complete the process on the gates (permanent code).  

Thank you for your patience in all of these matters.  At least we don't have rabbit issues.

Oh wait.  Never mind.

###